OFOF Home
OFOF Photos
View From On Top
EAA 1112 Home
OFOF Briefing Hut
Electrics Project
|
|
Oroville Foundation of Flight Achievements
Milestones
Foundation Formed
Site Indentified
Site Lease Approved
Agreement Reached w/ Golf Course for entry off Wes Barrett Dr.
Site Plan Developed and Approved
Water Service Installed
Hanger Site Developed
Terry's Glen Landscaped
Mower Rebuilt and Regular Mowing Established
Tom Toolcrib Built
Taxiway Constructed
Parking Area and Adjacent gravel surfaced
Donor's Wall/Flagpole Supports Constructed
Central Flagpole Installed
Site Dedication/Flag Ceremony - 7/4/99 - Rep. Wally Herger
Tree Landscaping Planted
Automatic Sprinkler System Installed
Flagpoles #2 and #3 installed 8/24/00
"Briefing Hut" disassembled at AFC site - 8/31 and 9/5/00
Hut pad poured - 10/4/00
Electrical cable buried and meter box/pole set - 10/6/00
Briefing Hut reassembled on pad with South wall and Roof all in place
Breaker box installed and breakers in place
Breaker box wired with service cable, 220v receptacle and double 110v GFCI receptacles
PG&E installe the meter at the power pole and turned on the power on 11/17/00
West door installed to allow access without having to open North wall
Ramp leading from parking lot to West door paved with gravel and packed
North Wall installed - 12/7/00 - Hut is now weather resistant
Sink and counter installed in SE corner of Hut
Two banks of five each overhead fluorescent light fixtures installed
Receptacles installed inside on east, south and west walls, two receptacles at the sink
An inside light and an outside "porch" light installed at the east and west doors
Outside receptacles installed at north ends of east and west walls
Underground power installed to Donors Wall and to the sprinkler timer in Terry's Glen
Sprinkler timer converted from battery operated to 110vac operated with new power line
Water line extended from Donor's Wall to the SE corner of parking lot (same trench as UG power)
Gray water drain, sump and outflow line installed at south end of Hut
Winch operated opening scheme built for east side of North wall
Water supply and drain installed for sink
North wall zipper repaired by replacement
North wall tears and worn spots repaired by adhesive attached overlay
South wall top closed in with "Wind Seals" to prevent top raising in wind and rain blowing in
North wall hold downs replaced with Toggle Clamps to facilitate opening and closing operations
Decomposed Granite (DG) paving applied to east 150 ft. adjoining taxiway - 10/14/01
DG paving applied to pad immediately north of Hut, 100 ft x 50 ft area - 10/14/01
Agenda
Research Funding/Grant Opportunities - A continuous process
Pave Ramp - DONE
Pave Taxiway - Partially done
Organize Instruction - Two classes held. Riveting (Bob Foster, Terry Hodges) and basic fabric covering (Agviation, John Burg)
Provide Instruction - see above
Build Projects - Joe Cook's UL project has moved inot PS#1. Chuck/Cat Heindell's CA65 project is scheduled for PS#2 as of 1/1/02.
Fly Projects
et al
Last Update 01/09/02
|